Ratio & Proportion — Drill 2 is a focused CLAT UG topic drill for targeted practice on one topic. Attempt it free in a real CLAT exam-screen interface with a live countdown timer, question palette, instant scoring and detailed solutions for every question.
The first 5 questions of this test, with answers and solutions. Try them on the exam screen above first.
A construction contractor records that 12 workers, all working at the same steady rate, complete a stretch of road in 18 days. The contractor plans the same job with different team sizes. The amount of work is fixed, so the number of workers and the number of days needed vary inversely.
How many days would 9 workers take to complete the same road?
Answer: (C)
Total work = 12 x 18 = 216 worker-days. With 9 workers, days = 216 / 9 = 24 days.
If the contractor deploys 24 workers, how many days are needed?
Answer: (A)
Days = 216 / 24 = 9 days, since work stays at 216 worker-days.
How many workers are required to finish the road in exactly 6 days?
Answer: (D)
Workers = 216 / 6 = 36 workers.
How many days would 18 workers take?
Answer: (B)
Days = 216 / 18 = 12 days.
If only half the road needs paving, how many days would the original 12 workers take?
Answer: (C)
Half the work = 216 / 2 = 108 worker-days. With 12 workers, days = 108 / 12 = 9 days.
Explore more free CLAT practice: all mock tests, previous-year papers, or review the CLAT syllabus & exam pattern.