A construction supervisor records that 12 workers can build a boundary wall in 18 days, with every worker doing the same amount of work each day. The number of workers and the number of days are inversely proportional for this fixed wall.
How many days would 16 workers take to build the same wall?
Answer: (C)
Total work = 12 x 18 = 216 worker-days. Days = 216/16 = 13.5 days.
How many days would 9 workers take to build the same wall?
Answer: (A)
Days = 216/9 = 24 days.
How many workers are needed to finish the wall in 8 days?
Answer: (D)
Workers = 216/8 = 27 workers.
How many workers are needed to finish the wall in 12 days?
Answer: (B)
Workers = 216/12 = 18 workers.
In how many days would 24 workers complete the same wall?
Answer: (C)
Days = 216/24 = 9 days.